This wiki has undergone a migration to Confluence found Here
<meta name="googlebot" content="noindex">

Difference between revisions of "FHIR Ballot Prep"

From HL7Wiki
Jump to navigation Jump to search
Line 10: Line 10:
 
** Previously published resources meet the [[DSTU 2 QA guidelines]] (work groups have signed off the resources in the [https://docs.google.com/a/lmckenzie.com/spreadsheets/d/18HfXF7mUCUV7jACCG0oejFp6D-ibtvbmcgywNhn76lw QA tracking Google sheet])
 
** Previously published resources meet the [[DSTU 2 QA guidelines]] (work groups have signed off the resources in the [https://docs.google.com/a/lmckenzie.com/spreadsheets/d/18HfXF7mUCUV7jACCG0oejFp6D-ibtvbmcgywNhn76lw QA tracking Google sheet])
 
** New resources are complete, ready for QA and also signed off in the QA tracking Google sheet
 
** New resources are complete, ready for QA and also signed off in the QA tracking Google sheet
** Profiles have been defined for all [[WG resources needed to cover CCDA 1.2]]
+
** Profiles have been defined for all [https://docs.google.com/a/lmckenzie.com/spreadsheets/d/18HfXF7mUCUV7jACCG0oejFp6D-ibtvbmcgywNhn76lw WG resources needed to cover CCDA 1.1]
 
** All tracker items have either been identified has having changes deferred to a subsequent release or have had those changes applied
 
** All tracker items have either been identified has having changes deferred to a subsequent release or have had those changes applied
 
** FHIR "build" is clean and produces no error or warning messages
 
** FHIR "build" is clean and produces no error or warning messages

Revision as of 17:40, 14 May 2014

This page lists the tasks to be completed by work groups in preparation for the second DSTU release of FHIR. The tentative schedule for this release is as follows:

  • May 16th
    • All WGs doing FHIR work have Project Scope Statements defining their scope for the next DSTU release completed and in progress through the publication cycle. This will likely require new PSSs or modifications of existing PSSs.
    • All WGs developing new resources or developing profiles other than CCDA R2 profiles have submitted resource proposals or profile proposals to the FMG describing their intended work
  • May 30th
    • All PSSs are approved
    • All resource & profile proposals have been finalized and approved and placeholders exist in SVN for all new work
    • WG editors have a functioning SVN build environment
  • Sept 21 (Sunday after WGM)
    • Previously published resources meet the DSTU 2 QA guidelines (work groups have signed off the resources in the QA tracking Google sheet)
    • New resources are complete, ready for QA and also signed off in the QA tracking Google sheet
    • Profiles have been defined for all WG resources needed to cover CCDA 1.1
    • All tracker items have either been identified has having changes deferred to a subsequent release or have had those changes applied
    • FHIR "build" is clean and produces no error or warning messages
  • Oct. 12
    • QA is complete and distributed to WGs
  • Nov 24
    • Content is final for ballot
  • Jan WGM
    • Ballot feedback is reviewed
  • Feb 28, 2015
    • Reconciliation complete and changes applied
  • Mar 31, 2015
    • QA complete, DSTU R2 published