This page lists the tasks to be completed by work groups in preparation for the second DSTU release of FHIR.  The tentative schedule for this release is as follows:
+
 
* Sept 29th
+
This page lists the tasks to be completed by work groups in preparation for the DSTU 2.1 interim release of the FHIR core specification.  The timelines for implementation guide publication and balloting may differ.  Implementation Guides may choose to either publish in sync with the core specification (and actively manage dependencies as underlying resources and profiles are updated) or may choose to ballot later, once the FHIR specification is finalized(The disadvantage of the latter approach is that changes to the core specification identified as part of implementation guide revision won't be able to be applied until a subsequent release) 
** All WGs doing FHIR work have Project Scope Statements defining their scope for the next DSTU release completed and in progress through the publication cycleThis will likely require new PSSs or modifications of existing PSSs.
+
 
** All WGs developing new resources or developing profiles other than CCDA R2 profiles have submitted resource proposals or profile proposals to the FMG describing their intended work
+
 
* Oct 15th
+
The tentative schedule for this release is as follows:
** All PSSs are approved
+
* Oct 17th, 2015
** All resource & profile proposals have been finalized and approved and placeholders exist in SVN for all new work
+
** DSTU 2 patch published
** WG editors have a functioning SVN build environment
+
** Substantive changes for non-frozen resources and non-substantive changes for all resources can be committed (wait for announcement on committer's list)
* Dec 5
+
* Oct 30th, 2015
** All content intended for inclusion DSTU 2 is complete in at least draft form and ready for Draft for Comment ballot
+
** All work groups should have active PSSs for 2.1 (and ideally 3.0) FHIR development work
* Jan 15
+
* Nov 30th
** Draft for Comment results available, reconciliation begins
+
** Proposals for new resources and profiles for inclusion in DSTU 2 are submitted to the FMG
* Mar 22
+
** All substantive changes applied for connectathon release
** Previously published resources meet the [[DSTU 2 QA guidelines]] (work groups have signed off the resources in the [https://docs.google.com/a/lmckenzie.com/spreadsheets/d/18HfXF7mUCUV7jACCG0oejFp6D-ibtvbmcgywNhn76lw QA tracking Google sheet])
+
** Connectathon release published
** New resources are complete, ready for QA and also signed off in the QA tracking Google sheet
+
* Jan 9, 2016
** ''DEFERRED until post DSTU ballot'': Profiles have been defined for all [https://docs.google.com/a/lmckenzie.com/spreadsheets/d/18HfXF7mUCUV7jACCG0oejFp6D-ibtvbmcgywNhn76lw WG resources needed to cover CCDA 1.1] (2nd tab)
+
** Resource and profile proposals approved by the FMG
** All tracker items have either been identified has having changes deferred to a subsequent release or have had those changes applied
+
* Jan 9, 2015
** FHIR "build" is clean and produces no error or warning messages
+
** Connectathon
* Last 1.5 weeks of March
+
* Mar 18
** DSTU QA process
+
** Final content freeze
* April 3, 2015
+
** Start of QA process
** DSTU ballot opens
+
* Mar 215
* May 4, 2015
 
** DSTU Ballot closes
 
* August 31, 2015
 
** FHIR Core reconciliation complete and final content ready for QA
 
* Sept 7, 2015
 
** IG reconciliation complete and final content ready for QA
 
* Sept 14, 2015
 
 
** QA complete
 
** QA complete
* ~ 3rd week of Sept, 2015
+
** Apply QA changes
** DSTU 2 is published
+
* April 1
 +
** DSTU 2.1 ballot opens
 +
* May 2
 +
** DSTU 2.1 Ballot closes
 +
* May 7, 2016
 +
** Ballot triage complete
 +
 
 +
Note: The following timelines are dependent on the volume of in-scope ballot requirements
 +
*June 30
 +
** Reconciliation complete
 +
* July 17
 +
** All changes applied
 +
** WGs have voted for content to progress from draft to FMM 1 and from FMM 3 to FMM 4
 +
* July 31
 +
** Publication QA complete
 +
* 1st week of August
 +
** DSTU 2.1 published, SVN opened for 3.0 commits
 +
 
 +
We'll worry about FHIR "release 3" timelines once 2.1 is published and there's a good idea of scope.

Revision as of 16:54, 14 October 2015

This page lists the tasks to be completed by work groups in preparation for the DSTU 2.1 interim release of the FHIR core specification. The timelines for implementation guide publication and balloting may differ. Implementation Guides may choose to either publish in sync with the core specification (and actively manage dependencies as underlying resources and profiles are updated) or may choose to ballot later, once the FHIR specification is finalized. (The disadvantage of the latter approach is that changes to the core specification identified as part of implementation guide revision won't be able to be applied until a subsequent release)


The tentative schedule for this release is as follows:

  • Oct 17th, 2015
    • DSTU 2 patch published
    • Substantive changes for non-frozen resources and non-substantive changes for all resources can be committed (wait for announcement on committer's list)
  • Oct 30th, 2015
    • All work groups should have active PSSs for 2.1 (and ideally 3.0) FHIR development work
  • Nov 30th
    • Proposals for new resources and profiles for inclusion in DSTU 2 are submitted to the FMG
    • All substantive changes applied for connectathon release
    • Connectathon release published
  • Jan 9, 2016
    • Resource and profile proposals approved by the FMG
  • Jan 9, 2015
    • Connectathon
  • Mar 18
    • Final content freeze
    • Start of QA process
  • Mar 215
    • QA complete
    • Apply QA changes
  • April 1
    • DSTU 2.1 ballot opens
  • May 2
    • DSTU 2.1 Ballot closes
  • May 7, 2016
    • Ballot triage complete

Note: The following timelines are dependent on the volume of in-scope ballot requirements

  • June 30
    • Reconciliation complete
  • July 17
    • All changes applied
    • WGs have voted for content to progress from draft to FMM 1 and from FMM 3 to FMM 4
  • July 31
    • Publication QA complete
  • 1st week of August
    • DSTU 2.1 published, SVN opened for 3.0 commits

We'll worry about FHIR "release 3" timelines once 2.1 is published and there's a good idea of scope.