This wiki has undergone a migration to Confluence found Here
Difference between revisions of "September 2009 WGM Agenda CBCC Wednesday Q4"
Jump to navigation
Jump to search
Finaversaggi (talk | contribs) |
|||
(2 intermediate revisions by one other user not shown) | |||
Line 15: | Line 15: | ||
*'''SWOT''' | *'''SWOT''' | ||
* SWOT updates finalized during this session. Updated version will be placed on the CBCC Wiki site and on GForge | * SWOT updates finalized during this session. Updated version will be placed on the CBCC Wiki site and on GForge | ||
− | **''''' | + | **'''''[http://wiki.hl7.org/index.php?title=CBCC_SWOT_as_of_Sept_2009 SWOT document]''''' |
**Risk Assessments: eliminate some of the barriers that prevent a project from moving forward; reign in the scope instead of working on things that will never be productive; mitigate the project’s risks | **Risk Assessments: eliminate some of the barriers that prevent a project from moving forward; reign in the scope instead of working on things that will never be productive; mitigate the project’s risks | ||
**Security Work Group is working on a process for Risk Assessment. Other Work Groups can request advice on Security risks to their projects. The Security Work Group will assign someone to help | **Security Work Group is working on a process for Risk Assessment. Other Work Groups can request advice on Security risks to their projects. The Security Work Group will assign someone to help | ||
Line 28: | Line 28: | ||
*Seconded by Max | *Seconded by Max | ||
− | Meeting adjourned at 5:00 PM EST | + | Meeting adjourned at 5:00 PM EST. No significant decisions or motions made |
+ | |||
+ | [[Community-Based_Collaborative_Care|Back to CBCC Main Page]] | ||
+ | |||
+ | [[http://wiki.hl7.org/index.php?title=September_2009_WGM_Agenda_CBCC_Wednesday_Q4 Top]] |
Latest revision as of 03:27, 19 January 2010
Community-Based Collaborative Care Working Group
Attendees
- Suzanne Gonzales-Webb
- Ray Krasinski
- Nancy LeRoy
- Rob McClure
- Harry Rhodes
- Richard Thoreson co-chair
- Serafina Versaggi Scribe
- Max Walker co-chair
Unfinished Project Planning
- SWOT
- SWOT updates finalized during this session. Updated version will be placed on the CBCC Wiki site and on GForge
- SWOT document
- Risk Assessments: eliminate some of the barriers that prevent a project from moving forward; reign in the scope instead of working on things that will never be productive; mitigate the project’s risks
- Security Work Group is working on a process for Risk Assessment. Other Work Groups can request advice on Security risks to their projects. The Security Work Group will assign someone to help
- Risk Assessment Process: writing down risks and their mitigation strategy helps to keep common sense approaches in the forefront of the project planning process and allows things to be re-prioritized in the event the likelihood of a risk occurring goes up as changes to the environment occur
- Three-Year Plan
- Three-Year plan updated during this session and will be placed on the CBCC Wiki site and on GForge
- Need to add timelines to the spreadsheet – will be done offline, reviewed and approved during an upcoming conference call
- Ioana: please insert the updated 3-Year Plan
Suzanne: Motion to adjourn meeting
- Seconded by Max
Meeting adjourned at 5:00 PM EST. No significant decisions or motions made
[Top]