==Detailed schedule== | ==Detailed schedule== | ||
''For comment ballot'' | ''For comment ballot'' | ||
− | + | :2017-10-25 - Work groups inform the FMG of any implementation guides they'd like to ballot in Dec. cycle (strong preference to not ballot against R3 at this time unless essential for regulatory or similar reasons) | |
− | 2017-10-25 - Work groups inform the FMG of any implementation guides they'd like to ballot in Dec. cycle (strong preference to not ballot against R3 at this time unless essential for regulatory or similar reasons) | + | :2017-11-15 - Work groups identify any changes (additions or removals) to the candidate list of Normative content |
− | |||
− | 2017-11-15 - Work groups identify any changes (additions or removals) to the candidate list of Normative content | ||
*Framework, XML, JSON, RESTful API, Search | *Framework, XML, JSON, RESTful API, Search | ||
*CodeSystem, ValueSet, ConceptMap. (But not all operations on those resources) | *CodeSystem, ValueSet, ConceptMap. (But not all operations on those resources) | ||
Line 31: | Line 29: | ||
*Patient, Observation | *Patient, Observation | ||
− | 2017-12-10 - Substantive change freeze for core. | + | :2017-12-10 - Substantive change freeze for core. |
*Normative candidates SHOULD have QA spreadsheet filled in and pass all QA. Related change logs should be clear. Should be no "Deferred" substantive changes | *Normative candidates SHOULD have QA spreadsheet filled in and pass all QA. Related change logs should be clear. Should be no "Deferred" substantive changes | ||
*Any resource intended to be in R4 needs to be present in at least draft form | *Any resource intended to be in R4 needs to be present in at least draft form | ||
− | + | :2017-12-17 - Final freeze (including IGs) | |
− | 2017-12-17 - Final freeze (including IGs) | + | :2017-12-22 - Ballot opens |
− | + | :2018-01-22 - Ballot closes | |
− | 2017-12-22 - Ballot opens | + | :2018-01-27 - 2018-02-02: Jan WGM (New Orleans) |
− | |||
− | 2018-01-22 - Ballot closes | ||
− | |||
− | 2018-01-27 - 2018-02-02: Jan WGM (New Orleans) | ||
''Primary ballot'' | ''Primary ballot'' | ||
+ | :2018-02-14 - Last date to inform FMG of intention to ballot IGs as part of May ballot. | ||
+ | :2018-03-04 - FHIR Core substantive change freeze. IGs can still make changes. Work groups must inform product director what resources are to be treated as "draft" for this ballot (and for R4). | ||
+ | :2018-03-11 - FHIR Core content total freeze. Normative candidates SHALL have QA spreadsheet filled in and pass all QA. Normative content should have tracker items cleared and no outstanding deferred QA tracker items. QA period opens for core and IG processes | ||
+ | * Note: After this date, substantive changes can only be made to artifacts and pages marked "Normative" if they are in response to a ballot comment or the artifact has been dropped from its normative package back to STU status | ||
+ | :2018-03-25 - QA changes may be applied | ||
+ | :2018-04-01 - Final content freeze - no changes except with permission of product director | ||
+ | :2018-04-06 - Ballot opens | ||
+ | :2018-05-07 - Ballot closes | ||
+ | :2018-05-12 - 2018-05-18: May WGM (Cologne) | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
''Optional 3rd ballot'' | ''Optional 3rd ballot'' | ||
− | + | :2018-07-01: Work groups notify the FMG whether they need to reballot normative packages (due to substantive change), STU resources (due to significant refactoring) or IGs during the Sept. cycle | |
− | 2018-07-01: Work groups notify the FMG whether they need to reballot normative packages (due to substantive change), STU resources (due to significant refactoring) or IGs during the Sept. cycle | + | :2018-08-10: All substantive reconciliation applied. FHIR Core is frozen, limited QA process for content subject to ballot only |
− | + | :2018-08-17: Pre-ballot (and connectathon) content freeze. Publication process begins, including ensuring that content is appropriately flagged for ballot status and there are no last minute QA issues | |
− | 2018-08-10: All substantive reconciliation applied. FHIR Core is frozen, limited QA process for content subject to ballot only | + | :2018-08-24: OptionalBallot opens |
− | + | :2018-09-24: Ballot closes and initial triage occurs. Note: No substantive changes allowed for normative candidates unless they drop to STU. | |
− | 2018-08-17: Pre-ballot (and connectathon) content freeze. Publication process begins, including ensuring that content is appropriately flagged for ballot status and there are no last minute QA issues | ||
− | |||
− | 2018-08-24: OptionalBallot opens | ||
− | |||
− | 2018-09-24: Ballot closes and initial triage occurs. Note: No substantive changes allowed for normative candidates unless they drop to STU. | ||
''Final content changes and publication'' | ''Final content changes and publication'' | ||
− | + | :2018-09-29 - 2018-10-05: October WGM (Baltimore). | |
− | 2018-09-29 - 2018-10-05: October WGM (Baltimore). | + | :2018-10-14: Final reconciliation packages posted for 2nd and 3rd ballots |
− | + | :2018-11-01: Substantive content freeze for core R4 publication including all substantive QA changes. Decision based on vote results and withdrawals about which normative packages to drop to STU. Implementation guides publishing as part of R4 may continue to make substantive changes. | |
− | 2018-10-14: Final reconciliation packages posted for 2nd and 3rd ballots | + | :2018-11-11: Final content freeze for R4 publication and start of QA period. No changes permitted for FHIR Core without product director permissions. Implementation Guides may update based on their QA processes |
− | + | :2018-11-25: QA period closes, QA change application begins | |
− | 2018-11-01: Substantive content freeze for core R4 publication including all substantive QA changes. Decision based on vote results and withdrawals about which normative packages to drop to STU. Implementation guides publishing as part of R4 may continue to make substantive changes. | + | :2018-12-02: FHIR core and FHIR IGs are all locked. No further changes without product director permission |
− | + | *Finalization of FMM levels, final internal publication clean-up, publication process, TSC publication approval | |
− | 2018-11-11: Final content freeze for R4 publication and start of QA period. No changes permitted for FHIR Core without product director permissions. Implementation Guides may update based on their QA processes | + | :~2018-12-15: Publication of R4 |
− | |||
− | 2018-11-25: QA period closes, QA change application begins | ||
− | |||
− | 2018-12-02: FHIR core and FHIR IGs are all locked. No further changes without product director permission | ||
− | Finalization of FMM levels, final internal publication clean-up, publication process, TSC publication approval | ||
− | |||
− | ~2018-12-15: Publication of R4 | ||
The world rejoices, Grahame sleeps | The world rejoices, Grahame sleeps | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Revision as of 19:09, 11 September 2017
This page lists the tasks to be completed by work groups in preparation for the R4 release of the FHIR core specification. The timelines for implementation guide publication and balloting may differ. Implementation Guides may choose to either publish in sync with the core specification (and actively manage dependencies as underlying resources and profiles are updated) or may choose to ballot later, once the FHIR specification is finalized. (The disadvantage of the latter approach is that changes to the core specification identified as part of implementation guide revision won't be able to be applied until a subsequent release)
The current schedule for the next connectathon/ballot base (Jan 2018)
- Oct 18th - connectathon proposal deadline
- Freeze deadlines will be the same as the Dec. ballot deadlines below:
Ballot schedule
Note that this schedule is considered to be quite firm. If there are concerns about meeting the target dates listed here, the likely outcome will be changing ballot status of artifacts (Normative down to STU, STU down to draft, lower FMM levels, drop content entirely). That said, if you have concerns about any of these dates, please contact your work group's FMG liaison or send an email to fmgcontact@hl7.org
Plan Overview
We expect that the R4 cycle will consist of 2-3 ballots:
- January 2018 Cycle - Single For Comment Ballot: The purpose of this ballot is to provide an early review of Normative content to ensure quality is in place and identify as many substantive issues as possible in advance of the normative ballot. It also provides a QA point for other resources as we prepare for the "real" ballot. Tracker items received as a result of this ballot don't require formal resolution or change application prior to the opening of the following ballot, though work groups should do their best - prioritizing normative - to resolve what they can. Unresolved commenets will carry forward but will not carry ballot weight unless someone references them in a subsequent ballot.
- May 2018 Cycle - Single STU ballot, multiple Normative ballots: This will be the "primary" ballot for R4. The normative content will be broken up into multiple packages (likely 3) to allow some packages to pass while others are dropped to 'STU' if necessary. FMM levels will be locked prior to this ballot and content here will require reconciliation. (Balloters might reference previously submitted tracker items, including items submitted as part of the For Comment ballot.)
- Sept 2018 Cycle - possible Normative re-ballots and limited STU ballot: The primary purpose of this cycle is to allow reballoting of packages that are eligible to pass with only minor substantive changes or where one or more resources have been dropped from the package down to STU. *If* there is a second ballot for normative issues, then work groups balloting STU core content may petition for an additional STU ballot if they've made major revisions they feel justifies an additional ballot review. However, STU publications do not require reballot for substantive change and there will be little time for reconciliation and change application prior to the publication of R4, so this option needs to be considered carefully.
Publication of R4 will occur in mid-December 2018.
Detailed schedule
For comment ballot
- 2017-10-25 - Work groups inform the FMG of any implementation guides they'd like to ballot in Dec. cycle (strong preference to not ballot against R3 at this time unless essential for regulatory or similar reasons)
- 2017-11-15 - Work groups identify any changes (additions or removals) to the candidate list of Normative content
- Framework, XML, JSON, RESTful API, Search
- CodeSystem, ValueSet, ConceptMap. (But not all operations on those resources)
- Bundle, OperationOutcome, Parameters, StructureDefinition, SearchParameter, CapabilityStatement, OperationDefinition
- Patient, Observation
- 2017-12-10 - Substantive change freeze for core.
- Normative candidates SHOULD have QA spreadsheet filled in and pass all QA. Related change logs should be clear. Should be no "Deferred" substantive changes
- Any resource intended to be in R4 needs to be present in at least draft form
- 2017-12-17 - Final freeze (including IGs)
- 2017-12-22 - Ballot opens
- 2018-01-22 - Ballot closes
- 2018-01-27 - 2018-02-02: Jan WGM (New Orleans)
Primary ballot
- 2018-02-14 - Last date to inform FMG of intention to ballot IGs as part of May ballot.
- 2018-03-04 - FHIR Core substantive change freeze. IGs can still make changes. Work groups must inform product director what resources are to be treated as "draft" for this ballot (and for R4).
- 2018-03-11 - FHIR Core content total freeze. Normative candidates SHALL have QA spreadsheet filled in and pass all QA. Normative content should have tracker items cleared and no outstanding deferred QA tracker items. QA period opens for core and IG processes
- Note: After this date, substantive changes can only be made to artifacts and pages marked "Normative" if they are in response to a ballot comment or the artifact has been dropped from its normative package back to STU status
- 2018-03-25 - QA changes may be applied
- 2018-04-01 - Final content freeze - no changes except with permission of product director
- 2018-04-06 - Ballot opens
- 2018-05-07 - Ballot closes
- 2018-05-12 - 2018-05-18: May WGM (Cologne)
Optional 3rd ballot
- 2018-07-01: Work groups notify the FMG whether they need to reballot normative packages (due to substantive change), STU resources (due to significant refactoring) or IGs during the Sept. cycle
- 2018-08-10: All substantive reconciliation applied. FHIR Core is frozen, limited QA process for content subject to ballot only
- 2018-08-17: Pre-ballot (and connectathon) content freeze. Publication process begins, including ensuring that content is appropriately flagged for ballot status and there are no last minute QA issues
- 2018-08-24: OptionalBallot opens
- 2018-09-24: Ballot closes and initial triage occurs. Note: No substantive changes allowed for normative candidates unless they drop to STU.
Final content changes and publication
- 2018-09-29 - 2018-10-05: October WGM (Baltimore).
- 2018-10-14: Final reconciliation packages posted for 2nd and 3rd ballots
- 2018-11-01: Substantive content freeze for core R4 publication including all substantive QA changes. Decision based on vote results and withdrawals about which normative packages to drop to STU. Implementation guides publishing as part of R4 may continue to make substantive changes.
- 2018-11-11: Final content freeze for R4 publication and start of QA period. No changes permitted for FHIR Core without product director permissions. Implementation Guides may update based on their QA processes
- 2018-11-25: QA period closes, QA change application begins
- 2018-12-02: FHIR core and FHIR IGs are all locked. No further changes without product director permission
- Finalization of FMM levels, final internal publication clean-up, publication process, TSC publication approval
- ~2018-12-15: Publication of R4
The world rejoices, Grahame sleeps