Difference between revisions of "SAIF Pilot Coordination Project"

From HL7Wiki
Jump to navigation Jump to search
Line 374: Line 374:
 
<td>'''Security:  Cookbook and MnM'''</td>
 
<td>'''Security:  Cookbook and MnM'''</td>
 
<td>Security, MnM</td>
 
<td>Security, MnM</td>
<td>Sept 2011 WGM</td>
+
<td>???</td>
<td>Oct 2011</td>
+
<td>???</td>
<td></td>  
+
<td>GForge Tracker 1945 focuses on determining the target date for this work</td>  
 
</tr>
 
</tr>
  

Revision as of 14:54, 24 August 2011

03-26-2011: PAGE UNDER CONSTRUCTION - Rick Haddorff Project Services

Return to Main Page - SAIF Architecture Program wiki page - Work Group main page

Project Information

Link to Project Insight Searchable Database Entry (keywords SAIF Pilot Coordination), which contains:

  • Brief description of project
  • Project facilitators
  • Summary of project scope statement


Meeting Information

Currently meeting along with SAIF Architecture Program


Status

Nothing in ballot at this time


Issues / Hot Topics

GForge ItemDescriptionNext StepsNotes/Links
1865Determine what steps needs to be completed to acquire the EA softwareLorraine Constable will document what steps they took to acquire EA software for the OO project and report to the team


Closed Issues / Deliverables

GForge ItemDescriptionDeliverableNotes/Links
1868Determine how to actually get the EA Software to the modelersThe process is documented in the Managing Sparx Enterprise

Architect License Distribution (via GForge > Tooling Documenation >

Files). Also Tracker 1865 is continuing work regarding this topic
Managing Sparx Enterprise Architect License Distribution
1868Pilot Coordination Deliverable: For Orders and Observations Behavioral Framework tooling selection (Enterprise Architecture): Document the relationships for who needs to be involved so the next tool we need we know who to go to and what steps to complete to obtain the software.RASCI chartRASCI OO EA Tool


Project Documents

Project Schedule

WORK IN PROGRESS
% CompleteTask NameWork GroupsStart DateEnd DateComments
100% Project Services: Populate SAIF Pilot Coordination wiki page Project Services May 2011 WGM May 2011 WGM Create SAIF Pilot Coordination wiki page
100% Tooling: Enterprise Architecture for OO Composite Order BF project/licensing Tooling, OO May 2011 WGM June 2011 GForge trackers 1865 and 1868. Jane is working on gathering this
100%     Pilot Coordination Deliverable: Document the relationships for who needs to be involved so the next tool we need we know who to go to and what steps to complete to obtain the software.
100%     Pilot Coordination Deliverable: Document what needs to be done to procure an EA license for those who need it
0% InM, OO: Wrappers-Need lead resources for OO CO project InM, OO Sept 2011 WGM Oct 2011 OO CO project needs someone from INM or the Wrappers project to lead the Wrappers portion of OO CO project. Gforge Tracker 1864.
0%     Pilot Coordination Deliverable: Insure that the SAIF Implentation Guide has documented the need for a Wrapper Facilitator in the SAIF
0% Governance: Ongoing documentation as relationships discovered SAIF AP Team will determine the responsible WG Sept 2012 WGM Oct 2012
0%     Pilot Coordination Deliverable: Will probably be suggestions for the SAIF Governance Framework document
0% Security, OO Struc Docs: Include Security Cookbook in OO CO and SDWG CDA R3 projects Security, OO, Struc Docs ??? ??? GForge Tracker 1945 focuses on determining the target date for this work
0%     Pilot Coordination Deliverable: Not sure. Need to ask the SAIF AP team how to go about this task.
0% OO/EHR-S FP: Define functional profile for composite order and lab order EHR, OO Sept 2011 WGM Oct 2011 EHR and OO work together to do this. Actual target date will be determined by the OO CO project schedule.
0%     Project Specific Deliverable: From the OO CO project; the Functional profile is the project specific deliverable.
0%     Pilot Coordination Deliverable: Documenting how the EHR group provided input to OO for the profile in the future SAIF IG
0% Tooling: Updating generator to create the new technical artifacts for BF Tooling, OO Sept 2011 WGM Oct 2011 Tooling and OO work together to do this. Actual target date will be determined by the OO BF project schedule.
0%     Project Specific Deliverable: From the OO BF project: An updated generator.
0%     Pilot Coordination Deliverable: Document the Tooling/OO coordination work in the future SAIF IG.
0% Publishing and MnM: What parts/pieces are in ballot Publishing, MnM Jan 2012 WGM Feb 2012 Part of the OO CO project, needing to know how to ballot. Actual target date will be dictated by the SAIF IG project
0%     Project Specific Deliverable:Part of the OO CO project; document this in the current SAIF IG (project being run by MnM)
0%     Pilot Coordination Deliverable: With the new SAIF artifacts, document what will need to be balloted, how will it impact preparing for balloting and balloting
0% ITS: What do the schemas look like? ITS, OO Sept 2011 WGM Oct 2011 From the OO CO project, how are they going to get the schemas generated with SAIF? Actual target date will be determined by the OO CO project schedule.  
0%     Project specific Deliverable: From the OO CO project, will be schemas that were produced.
0%     Pilot Coordination Deliverable: Document how to get the schemas generated with SAIF in the future SAIF IG.
0% SOA: Composite order and lab order need to include services for lab ordering SOA, OO Sept 2011 WGM Oct 2011 Actual target date will be determined by the OO CO project schedule.
0%     Project Specific Deliverable: From the OO CO project, the project has requested someone from SOA to be a facilitator (called a SOA Facilitator).
0%     Pilot Coordination Deliverable: Document the relationship and reason the SOA Facilitator was needed. Not sure where the documentation will ultimately reside; perhaps in the Goveranance documentation?
0% MnM: Maybe new fields and/or classes to support new BF MnM, OO TBD TBD Coordination between MnM and OO BF project. Actual target date will be determined by the OO BF project schedule.
0%     Project Specific Deliverable: From the OO BF project; possible changes to the RIM (New fields/classes).
0%     Pilot Coordination Deliverable: The coordination between MnM and OO may need to be documented in the Governance document.
0% ArB, MnM: New methodology, diagramming, pieces/parts that go in the ballot to define BF, including technical artifacts ArB, MnM Sept 2011 WGM Oct 2011 Actual target date will be determined by the OO BF project schedule.
0%     Project Specific Deliverable: To document this in the current SAIF IG (project run by MnM).
0%     Pilot Coordination Deliverable: No real deliverable; just insure that MnM has documented it in current SAIF IG.
0% Templates: Normative approved approach for HL7 template. OO project includes a Lab Order template which constrains the over-arching composite order model Templates, OO Jan 2012 WGM Feb 2012 Coordination between OO and Templates. Actual target date was determined by the OO CO project #587 when the Development of Technical Artifacts step was completed.
0%     Project Specific From the OO CO Project; Deliverable will be be a template
0%     Pilot Coordination Deliverable: Document the relationship between OO and Templates in the Governance document
0% Security: Cookbook and MnM Security, MnM ??? ??? GForge Tracker 1945 focuses on determining the target date for this work
0%     Project specific deliverable: From the MnM SAIF IG project Create the Security portion of the current SAIF IG.
0%     Pilot Coordination Deliverable: No real deliverable; just insure that MnM has documented it in current SAIF IG.
0% Security, CBCC: Confidentiality codes coordination needed between CDA R3 and OO and Security/CBCC Security, CBCC Jan 2012 WGM Feb 2012
0%     Project Specific Deliverable: Harmonization between the groups on how to create new confidentialy codes or use existing codes
0%     Pilot Coordination Deliverable: Document who had to be part of the process and what the process is in the future SAIF IG
0% Structured Docs: Information model consistency (CDA R3 project) ??? Jan 2012 WGM Feb 2012
0%     Project Deliverable: From CDA R3 project: One instance/example is the modeling of citizenship in CDA R3 (Coordination between CDA R3 and how it's been currently modeled by PA)
0%     Pilot Coordination Deliverable: Governance document will address information model consistency
0% Quality Plan Documentation ??? Sept 2011 WGM Oct 2011 Details TBD--refer to Gregg Seppala's modified Quality Plan PSS and subsequent discussions.
0%     Project Deliverable: (Phase A) Define the Artifact Quality Metrics
0%     Pilot Coordination Deliverable: (Phase A) Document the quality plan metrics in the quality steps of the PLCPD
0%     Project Deliverable: (Phase B) Identify and document process quality measures of the SAIF IG project
0%     Pilot Coordination Deliverable: (Phase B) Insure the quality measures are included in the Governance document
0%     Project Deliverable: (Phase C) Produce and ballot the SAIF IG for which the Quality Plan will define progress measures
0%     Pilot Coordination Deliverable: (Phase C) No real deliverable; just insure that MnM has documented it in current SAIF IG.