Line 23: Line 23:
 
* Current status - PSS approved by Pharmacy - being reviewed and approved by FMG, DESD, and TSC
 
* Current status - PSS approved by Pharmacy - being reviewed and approved by FMG, DESD, and TSC
 
** plan to ballot in January cycle
 
** plan to ballot in January cycle
 +
** See project page [[MedicationKnowledge FHIR Resource]]
  
 
===Project 1291 - Pharmacy FHIR Profiles Project===
 
===Project 1291 - Pharmacy FHIR Profiles Project===

Latest revision as of 13:47, 28 September 2017

Related Links

Active Projects/Ballots

Project TBD - MedicationKnowledge FHIR Resource

  • Current status - PSS approved by Pharmacy - being reviewed and approved by FMG, DESD, and TSC

Project 1291 - Pharmacy FHIR Profiles Project

  • aka US Meds
  • Current status - STU - Test Period/Accepting Comments

Project 1139 - Pharmacy Universal CDA Templates

  • Current Status - Balloted MedStatement and MedOrder as Comment only - September 2017 - in ballot reconciliation

Project 1239 - HL7 Pharmacy FHIR Updates

  • Current Status - active project

Project 1353 - Reaffirm HL7 V3 Standard: Medication Statement and Administration Event, Release 1

  • Current Status - draft PSS to be approved
  • needs to be reaffirmed by February 2018

Project 856 - Patient Medication Profile

  • Current status - 3 year plan item
Action:  Consider change to 3 year plan item - COMPLETE
  • Motion by S. Chu/J.Hatem to change Project 856 to a 3 year plan item with a target start date of January 2015 pending input from IHE Pharmacy (7/0/0)

Project 1220 - Pharmacy Glossary

  • Current status - 3 year plan item

Project 1221 - Pharmacy Webinar

  • Current status - 3 year plan item

Project 1270 -Formulary

  • Current status - 3 year plan item

Archived/Completed Projects

Project 249 - Pharmacy CMETs

  • Current status - Balloted in January 2013
Action: Post reconciliation package - Scott to post by End of Day November 18, 2013
Action: Make updates based on ballot comments
Action: Request publication
Action:  Melva to change next milestone to 30May2014 - COMPLETE
  • Motion by S. Chu/J.Hatem to approve change of the milestone to 30May2014 (7/0/0)

Project 501 - IDMP

  • Current status
    • Balloting 5 projects in January 2014
    • IDMP - Creation/Maintenance Messages - needs to be withdrawn
Action:  Withdrawal request for Creation/Maintenance Message Project/Material
Action:  change next milestone to 30Sept2014 - COMPLETE
  • Motion by S. Chu/J.Hatem to approve change of the milestone to 30Sept2014 (7/0/0)

Project 557 - Medication CMETs Release 1

  • Current Status
    • Balloted September 2013
Action: Make updates based on ballot comments
Action: Request publication
Action:  change next milestone to 30May2014 - COMPLETE
  • Motion by S. Chu/J.Hatem to approve change of the milestone to 30May2014 (7/0/0)

Project 558 - Medication Order Event Release 2

  • Current Status
    • Balloted - September 2013 - Next Milestone date 15Jan2014
Action:  Make updates based on ballot comments
Action:  Publication Request

Project 814 - Guidance on Implementation of Pharmacy Domain Messages

  • Current Status - 3 year plan item

Project 817 - Medication Dispense and Supply Event Release 2

  • Current Status
    • Balloted - September 2013 - Next Milestone date 15Jan2014
Action:  Make updates based on ballot comments
Action:  Publication Request

Project 842 - Medication Therapy Management (MTM) Templated CDA

  • Current Status - Balloting - January 2014 - Next Milestone date 15Jan2014
Action: Change target date to September 2014
  • Motion by S. Chu/J.Hatem to approve change of the milestone to 30Sept2014 (7/0/0)

Project 855 - Develop FHIR Resources for Pharmacy

  • Current Status
    • Balloted in September 2013
Action:  Finish ballot reconciliation
Action:  Make updates based on ballot comments
Action:  Ballot January 2014
Action:  Change target to May 30, 2014 - COMPLETE
  • Motion by S. Chu/J.Hatem to approve change of the milestone to 30May2014 (7/0/0)

Project 857 - Examination of pharmacy use cases to determine how our requirements can be met in CDA templates

  • Current Status - 3 year plan item

Project xxx - HL7 endorsement of externally developed "HL7 EHR-System for a Pharmacist/Pharmacy Electronic Health Record Implementation Guide for Community Practice"

  • Current status - PSS in circulation
Action:  Pharmacy WG approval of PSS
Action:  DESD and EHR WG approval of PSS
Action:  Create project in Project Insight
Action:  NIB for 2014MAY
Action:  Ballot open/close/adjudication
Action:  Document added to Pharmacy/Pharmacist EHR Functional Profile download page