Line 33: Line 33:
 
   * Determine skillsets needed for conversion
 
   * Determine skillsets needed for conversion
 
   * Estimate effort for conversion
 
   * Estimate effort for conversion
 +
 +
** Prepare communication plan
 +
  * Determine which groups need what kind of communication using what channels
 +
  * Determine skillsets needed for communication preparation
 +
  * Prepare estimate to create appropriate communication material for each audience
  
 
** Prepare to acquire suitable resources to support migration
 
** Prepare to acquire suitable resources to support migration
 
   * Prepare formal plan and estimate
 
   * Prepare formal plan and estimate
 
   * Acquire funding
 
   * Acquire funding
   * Acquire resources
+
   * Acquire resources
 
    
 
    
 
* Work Plan
 
* Work Plan

Revision as of 22:35, 1 October 2009

Planning for Implementation of Static Model Designer and other OHT projects.

Tasks (not in final order)

    • Test Application
 * Acquire test Plan
 * Update Test Plan for HL7 Use Cases
 * Make arrangements for tracking HL7 testers on OHT project trackers
 * Work out how to provide feedback and what needs to be resolved by the OHT project and what the Tooling WG will need to resolve
 * Get access to software
 * Determine technical requirements to install full package
 * Prepare documentation to assist testers to install package on different platforms

    • Perform Testing
 * Compare functionality with current tooling functionality and identify gaps
 * Identify whether gaps are bugs or missing capability or methodology issues
 * Prioritize fixes - identify which will be undertaken by the project and which to include in enhancement before deployment
 * Estimate effort to enhance before deployment
    • Evaluate Documentation
 * Examine documentation to determine if it is suitable to be able to support first time HL7 users.
 * Identify what documentation will be needed to distribute with HL7 users.
 * Estimate effort to enhance documentation before deployment
    • Prepare training plan
 * Identify topics needed for migration training
 * Identify sources of content for topics
 * Estimate effort to produce training material
    • Prepare conversion plan
 * Evaluate difficulty to convert existing models to be used by SMD.
 * Determine approach for conversion
 * Determine skillsets needed for conversion
 * Estimate effort for conversion
    • Prepare communication plan
 * Determine which groups need what kind of communication using what channels
 * Determine skillsets needed for communication preparation
 * Prepare estimate to create appropriate communication material for each audience
    • Prepare to acquire suitable resources to support migration
 * Prepare formal plan and estimate
 * Acquire funding
 * Acquire resources  
 
  • Work Plan