This wiki has undergone a migration to Confluence found Here
Implementing OHT Static Model Designer in HL7
Jump to navigation
Jump to search
Planning for Implementation of Static Model Designer and other OHT projects.
Tasks (not in final order)
Prepare to Test Application
- Acquire Test Plan - Nov. 4 draft available
- Update Test Plan for HL7 Use Cases - Nov. 12 - HL7TestCases
- Recruit specific HL7 testers - Nov. 12 - HL7 Testers
- Make arrangements for tracking HL7 testers on OHT project trackers - Nov. 26
- Assemble test data - Nov. 26
- Work out how to provide feedback and what needs to be resolved by the OHT project and what the Tooling WG will need to resolve - Nov. 26
- Get access to software - Nov. 30
- Determine technical requirements to install full package - Nov. 26
- Acquire NHS documentation for installing and running SMD for NHS testers - Nov. 19
- Enhance documentation to assist testers to install package on different platforms - Nov. 26
Perform Testing
- Register HL7 testing and assign HL7 tests
- Compare functionality with current tooling functionality and identify gaps
- Identify whether gaps are bugs or missing capability or methodology issues
- Prioritize fixes - identify which will be undertaken by the project and which to include in enhancement before deployment
- Estimate effort to enhance before deployment
Evaluate Documentation
- Examine documentation to determine if it is suitable to be able to support first time HL7 users.
- Identify what documentation will be needed to distribute with HL7 users.
- Estimate effort to enhance documentation before deployment
Prepare training plan
- Identify topics needed for migration training
- Identify sources of content for topics
- Estimate effort to produce training material
Prepare conversion plan
- Evaluate difficulty to convert existing models to be used by SMD.
- Determine approach for conversion
- Determine skillsets needed for conversion
- Estimate effort for conversion
Prepare communication plan
- Determine which groups need what kind of communication using what channels
- Determine skillsets needed for communication preparation
- Prepare estimate to create appropriate communication material for each audience
- Identify existing ballot documentation that will require revision
- Prepare estimate to revise ballot documentation
Prepare to acquire suitable resources to support migration
- Prepare formal plan and estimate
- Acquire funding
- Acquire resources
Work Plan
Test Status Tracking
- Act Class Validation Tracking Sheet ActClassValidationTestTrackingSheet.zip