Planning for Implementation of Static Model Designer and other OHT projects.
Tasks (not in final order)
Prepare to Test Application
- Acquire Test Plan - Nov. 4 draft available
- Update Test Plan for HL7 Use Cases - Nov. 12 - HL7TestCases
- Recruit specific HL7 testers - Nov. 12 - HL7 Testers
- Make arrangements for tracking HL7 testers on OHT project trackers - Nov. 26
- Assemble test data - Nov. 26
- Work out how to provide feedback and what needs to be resolved by the OHT project and what the Tooling WG will need to resolve - Nov. 26
- Get access to software - Nov. 30
- Determine technical requirements to install full package - Nov. 26
- Acquire NHS documentation for installing and running SMD for NHS testers - Nov. 19
- Enhance documentation to assist testers to install package on different platforms - Nov. 26
Perform Testing
- Register HL7 testing and assign HL7 tests
- Compare functionality with current tooling functionality and identify gaps
- Identify whether gaps are bugs or missing capability or methodology issues
- Prioritize fixes - identify which will be undertaken by the project and which to include in enhancement before deployment
- Estimate effort to enhance before deployment
Evaluate Documentation
- Examine documentation to determine if it is suitable to be able to support first time HL7 users.
- Identify what documentation will be needed to distribute with HL7 users.
- Estimate effort to enhance documentation before deployment
Prepare training plan
- Identify topics needed for migration training
- Identify sources of content for topics
- Estimate effort to produce training material
Prepare conversion plan
- Evaluate difficulty to convert existing models to be used by SMD.
- Determine approach for conversion
- Determine skillsets needed for conversion
- Estimate effort for conversion
Prepare communication plan
- Determine which groups need what kind of communication using what channels
- Determine skillsets needed for communication preparation
- Prepare estimate to create appropriate communication material for each audience
- Identify existing ballot documentation that will require revision
- Prepare estimate to revise ballot documentation
Prepare to acquire suitable resources to support migration
- Prepare formal plan and estimate
- Acquire funding
- Acquire resources
Work Plan
Tracking Sheets
- Act Class ValidationMedia:ActClassValidationTestTrackingSheet.zip