Tasks (not in final order)
 
Tasks (not in final order)
 
    
 
    
** Prepare to Test Application
+
===Prepare to Test Application===
  * Acquire Test Plan - Oct. 29
+
* Acquire Test Plan - Oct. 29
  * Update Test Plan for HL7 Use Cases - Nov. 12
+
* Update Test Plan for HL7 Use Cases - Nov. 12
  * Make arrangements for tracking HL7 testers on OHT project trackers - Nov. 26  
+
* Make arrangements for tracking HL7 testers on OHT project trackers - Nov. 26  
  * Work out how to provide feedback and what needs to be resolved by the OHT project and what the Tooling WG will need to resolve - Nov. 26  
+
* Work out how to provide feedback and what needs to be resolved by the OHT project and what the Tooling WG will need to resolve - Nov. 26  
  * Get access to software - Nov. 30
+
* Get access to software - Nov. 30
  * Determine technical requirements to install full package - Nov. 26
+
* Determine technical requirements to install full package - Nov. 26
  * Acquire NHS documentation for installing and running SMD for NHS testers - Nov. 19
+
* Acquire NHS documentation for installing and running SMD for NHS testers - Nov. 19
  * Enhance documentation to assist testers to install package on different platforms - Nov. 26
+
* Enhance documentation to assist testers to install package on different platforms - Nov. 26
 
   
 
   
** Perform Testing
+
===Perform Testing===
  * Register HL7 testing and assign HL7 tests
+
* Register HL7 testing and assign HL7 tests
  * Compare functionality with current tooling functionality and identify gaps
+
* Compare functionality with current tooling functionality and identify gaps
  * Identify whether gaps are bugs or missing capability or methodology issues
+
* Identify whether gaps are bugs or missing capability or methodology issues
  * Prioritize fixes - identify which will be undertaken by the project and which to include in enhancement before deployment
+
* Prioritize fixes - identify which will be undertaken by the project and which to include in enhancement before deployment
  * Estimate effort to enhance before deployment
+
* Estimate effort to enhance before deployment
  
** Evaluate Documentation
+
===Evaluate Documentation===
  * Examine documentation to determine if it is suitable to be able to support first time HL7 users.
+
* Examine documentation to determine if it is suitable to be able to support first time HL7 users.
  * Identify what documentation will be needed to distribute with HL7 users.
+
* Identify what documentation will be needed to distribute with HL7 users.
  * Estimate effort to enhance documentation before deployment
+
* Estimate effort to enhance documentation before deployment
  
** Prepare training plan
+
===Prepare training plan===
  * Identify topics needed for migration training
+
* Identify topics needed for migration training
  * Identify sources of content for topics
+
* Identify sources of content for topics
  * Estimate effort to produce training material
+
* Estimate effort to produce training material
  
** Prepare conversion plan
+
===Prepare conversion plan===
  * Evaluate difficulty to convert existing models to be used by SMD.
+
* Evaluate difficulty to convert existing models to be used by SMD.
  * Determine approach for conversion
+
* Determine approach for conversion
  * Determine skillsets needed for conversion
+
* Determine skillsets needed for conversion
  * Estimate effort for conversion
+
* Estimate effort for conversion
  
** Prepare communication plan
+
===Prepare communication plan===
  * Determine which groups need what kind of communication using what channels
+
* Determine which groups need what kind of communication using what channels
  * Determine skillsets needed for communication preparation
+
* Determine skillsets needed for communication preparation
  * Prepare estimate to create appropriate communication material for each audience
+
* Prepare estimate to create appropriate communication material for each audience
  * Identify existing ballot documentation that will require revision
+
* Identify existing ballot documentation that will require revision
  * Prepare estimate to revise ballot documentation
+
* Prepare estimate to revise ballot documentation
  
** Prepare to acquire suitable resources to support migration
+
===Prepare to acquire suitable resources to support migration===
  * Prepare formal plan and estimate
+
* Prepare formal plan and estimate
  * Acquire funding
+
* Acquire funding
  * Acquire resources   
+
* Acquire resources   
 
    
 
    
* Work Plan
+
===* Work Plan===

Revision as of 14:17, 29 October 2009

Planning for Implementation of Static Model Designer and other OHT projects.

Tasks (not in final order)

Prepare to Test Application

  • Acquire Test Plan - Oct. 29
  • Update Test Plan for HL7 Use Cases - Nov. 12
  • Make arrangements for tracking HL7 testers on OHT project trackers - Nov. 26
  • Work out how to provide feedback and what needs to be resolved by the OHT project and what the Tooling WG will need to resolve - Nov. 26
  • Get access to software - Nov. 30
  • Determine technical requirements to install full package - Nov. 26
  • Acquire NHS documentation for installing and running SMD for NHS testers - Nov. 19
  • Enhance documentation to assist testers to install package on different platforms - Nov. 26

Perform Testing

  • Register HL7 testing and assign HL7 tests
  • Compare functionality with current tooling functionality and identify gaps
  • Identify whether gaps are bugs or missing capability or methodology issues
  • Prioritize fixes - identify which will be undertaken by the project and which to include in enhancement before deployment
  • Estimate effort to enhance before deployment

Evaluate Documentation

  • Examine documentation to determine if it is suitable to be able to support first time HL7 users.
  • Identify what documentation will be needed to distribute with HL7 users.
  • Estimate effort to enhance documentation before deployment

Prepare training plan

  • Identify topics needed for migration training
  • Identify sources of content for topics
  • Estimate effort to produce training material

Prepare conversion plan

  • Evaluate difficulty to convert existing models to be used by SMD.
  • Determine approach for conversion
  • Determine skillsets needed for conversion
  • Estimate effort for conversion

Prepare communication plan

  • Determine which groups need what kind of communication using what channels
  • Determine skillsets needed for communication preparation
  • Prepare estimate to create appropriate communication material for each audience
  • Identify existing ballot documentation that will require revision
  • Prepare estimate to revise ballot documentation

Prepare to acquire suitable resources to support migration

  • Prepare formal plan and estimate
  • Acquire funding
  • Acquire resources

* Work Plan